Tag Archives: Sellwood Bridge
The Sellwood Bridge is FINISHED!
…and here’s the WHOLE story on how it happened. Since 2008, the renovation of the Sellwood Bridge has been the defining reality of our life here at the shop. Construction has only been happening since 2011, but we’ve been there … Continue reading
Sellwood Bridge Update is there is NO MORE SELLWOOD BRIDGE UPDATE!
Are you here looking for your monthly fix of the Sellwood Bridge? Sorry, you’re outta luck. We ran our very last Sellwood Bridge Update column last month and any future news about the Bridge will have to come from your … Continue reading
Sellwood Bridge FINAL Update
The Bridge is FINISHED! Way, way back in 2010, Our Sellwood Bridge Update column began with these words: “It seems that every time our Client Shuttle starts across the Sellwood Bridge, a nervous voice will come from the back, asking ‘so… … Continue reading
The long strange trip is almost over
We’re closing in on the final few installments of our Sellwood Bridge Update column. For both of our fans out there, we’ll be closing with a retrospective of the Bridge construction, and a look at what a long strange trip … Continue reading
Sellwood Bridge Update- They’ve handed it over to the goats
Closer, closer, closer… the Sellwood Bridge is on schedule to completion in November. It’s just down to the detail stuff now. The south side sidewalk is being finished, traffic signs are coming in, the Taylor’s Ferry Turnaround is a fading … Continue reading
On-schedule, over budget, and artsy
The folks at the Sellwood Bridge Project are on-target for completion in November, so they’re checking off the final few things on their to-do list. As the project nears completion the final bills are coming in. The bad news is … Continue reading